Document prepared by:
Aurecon Hong Kong Limited

Unit 1608, 16/F, Tower B, Manulife Financial Centre, 
223 – 231 Wai Yip Street, Kwun Tong, Kowloon 
Hong Kong S. A. R.

T
F
E
W
+852 3664 6888
+852 3664 6999
hongkong@aurecongroup.com
aurecongroup.com


A close-up of a letter

AI-generated content may be incorrect.

 


Document control record

Document prepared by:

Company name

Registration number

Address line 1

Address line 2
Address line 3

 

T
F
E
W

Company telephone
Company fax
Company email
Company web

 

A person using Aurecon documents or data accepts the risk of:

a)         Using the documents or data in electronic form without requesting and checking them for accuracy against the original hard copy version.

b)         Using the documents or data for any purpose not agreed to in writing by Aurecon.

 

 

Document control                                                                                                  

Report title

Quarterly Environmental Monitoring and Audit (EM&A) Report – August to October 2024

Document code

QEM&A-03

Project number

P525672

File path

 

Client

Wing Tat Civil Engineering Co. Limited

Client contact

 

Client reference

 

Rev

Date

Revision details/status

Author

Reviewer

Verifier
(if required)

Approver

0

2024-11-11

Draft

Jason Man

F. C. Tsang

 

Kevin Li

1

2024-11-14

First Version

Jason Man

F. C. Tsang

 

Kevin Li

2

2024-11-18

Second Version

Jason Man

F. C. Tsang

 

Kevin Li

 

 

 

 

 

 

 

Current revision

2

 

 

Approval

Author signature

 

 

Certified by

Name

Jason Man

Name

F. C. Tsang

Title

Environmental Team Consultant

Title

Environmental Team Leader

 

Contents

Executive Summary. IV

1    Introduction. 1

1.1     Project Background. 1

1.2     Construction Works Programme. 2

1.3     Project Organisation. 2

1.4     Construction Works Programme and Construction Works Area. 3

1.5     Works undertaken during the Period. 3

2    Water Quality. 5

2.1     Monitoring Requirement. 5

2.2     Monitoring Location. 5

2.3     Monitoring Parameter and Frequency. 6

2.4     Action and Limit Level for Water Quality Monitoring.. 6

2.5     Event and Action Plan. 7

2.6     Results and Observations. 8

2.7     Quarterly Assessment of Construction Impacts on Suspended Solids at the Project Site. 8

3    Noise. 10

3.1     Monitoring Locations. 10

3.2     Noise Monitoring Parameter, Frequency and Duration. 10

3.3     Action and Limit Levels. 11

3.4     Results and Observations. 11

4    Ecology. 12

4.1     Freshwater Crab. 12

5    Waste Management. 16

6    Land Contamination. 17

7    Landscape and Visual. 18

7.1     Audit Requirements. 18

7.2     Results and Observations. 18

8    Cultural Heritage. 19

8.1     Archaeology. 19

8.2     Built Heritage. 19

9    Environmental Site Inspection and Audit. 13

9.1     Implementation Status of Environmental Mitigation Measures. 13

10     Summary of Monitoring Exceedance, Complaints, Notification of Summons and Prosecutions. 15

10.1      Summary of Exceedance. 15

10.2      Summary of Environmental Non-Compliance. 15

10.3      Summary of Environmental Complaint. 15

10.4      Summary of Environmental Summon and Successful Prosecution. 15

11     Conclusions and Recommendations. 16

11.1      Conclusion. 16

11.2      Comments/ Recommendations. 17

 

Appendices

Appendix 1.1   Construction Programme

Appendix 1.2   Project Organization Chart

Appendix 2.1   Event and Action Plans for Water Quality

Appendix 2.2   Graphical Presentation of Water Quality Monitoring

Appendix 3.1   Event and Action Plans for Noise

Appendix 3.2   Graphical Presentation of Noise Monitoring

Appendix 5.1   Waste Flow Table

Appendix 10.1   Complaint Log

Figures                                                                  

Figure 1.1 General Site Location Plan

Figure 1.2 Location of Work Areas for the Project

Figure 2.1 Impact Water Quality Monitoring Locations

Figure 3.1 Impact Noise Monitoring Locations

Figure 8.1 Area for Archaeological Survey

Tables

Table A1 Summary of Exceedance Records of Water Quality Monitoring

Table 1.1 Parties Involved in Project Organisation

Table 2.1 Summary of Impact Water Quality Monitoring Stations

Table 2.2 Parameters measured in the Impact Water Quality Monitoring

Table 2.3 Action and Limit Levels for Water Quality

Table 2.4 Action and Limit Levels of Water Quality

Table 2.5 Summary of Exceedance Records of Water Quality Monitoring

Table 3.1 Noise Monitoring Stations during Construction Phase

Table 3.2 Construction Noise Monitoring Parameter, Frequency and Duration

Table 3.3 Action and Limit Levels for Construction Noise Monitoring

Table 8.1 Mitigation Measures for Impacted Graded Historic Buildings

Table 9.1 Site Observations

Table 10.1 Summary of Exceedance Records of Water Quality Monitoring

 


 

Executive Summary

A1.     Drainage Services Department (DSD) has appointed Aurecon Hong Kong Limited (Aurecon) to undertake the Environmental Team services for the project and implement the EM&A works.

A2.     The construction works commenced on 20 February 2024.

A3.     This 3rd Quarterly Environmental Monitoring and Audit (EM&A) Report is prepared for Contract No. DC/2022/02 Drainage Improvement Works at Yuen Long – Stage 2 (hereinafter called the “Contract”). The report summaries the findings of the EM&A programme during the reporting period from 1 August to 31 October 2024.

Key Construction Works in the Reporting Period

A4.     A summary of construction activities undertaken during the reporting period is presented below:

Ha Che

§  Site Clearance Work

§  Breaking Ground;

§  Temporary Drainage Diversion

§  Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting; and

§  Sheet pilling & Backfilling and Compaction

Lin Fa Tei

§  Site Clearance Work

§  Breaking Ground;

§  Temporary Drainage Diversion; and

§  Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting

Tai Wo

§  No construction activities.

Sung Shan New Village

§  Site Clearance

§  Breaking Ground.

§  Temporary Drainage Diversion; and

§  Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting

Breaches of Environmental Quality Performance Limits (AL levels)

Water Quality

A5.     The summary of exceedance records during the reporting period is summarized in Table A1.

Table A1 Summary of Exceedance Records of Water Quality Monitoring

Parameter

No. of non-project related exceedances

Total No. of non-project related exceedances

No. of exceedance related to the Project

Total No. of exceedance related to the Project

AL

LL

AL

LL

Dissolved Oxygen (DO)

0

0

0

0

0

0

Turbidity

0

0

0

0

0

0

Suspended Solids (SS)

0

0

0

0

0

0

 

A6.     No Action Level or Limit Level exceedance was recorded for water quality monitoring during the reporting period.

Noise

A7.     No Action Level or Limit Level exceedance was recorded for construction noise monitoring during the reporting period.

Complaint Log

A8.     No environmental complaint was received in the reporting period.

Notification of Summons and Successful Prosecutions

A9.     No notification of summons or successful prosecutions was received in the reporting period.

Reporting Changes

A10.  Construction works at Tai Wo are only allowed during dry season (i.e. October to March) in accordance with Condition 3.2 of EP No.: EP-596/2021. Due to no construction activities conducted at Tai Wo during the reporting period, no impact noise monitoring, impact water quality monitoring and weekly site inspection at Tai Wo was carried out during the reporting period.

A11.  The noise monitoring at LFT_M7 have been suspended since 27 March 2024 due to the objection from property management office for providing access to designated monitoring location. The property management office formally refused our application of access right LFT_M7 on 29 May 2024. An alternative monitoring location LFT_M6 was proposed to replace LFT_M7 and agreed with the ER and the IEC on 29 May 2024 and 4 June 2024 respectively, impact noise monitoring was thus carried out at LFT_M6 from 4 June 2024 onward.


 

1              Introduction

1.1        Project Background

1.1.1        The Drainage Master Plan Studies for the Yuen Long, Kam Tin, Ngau Tam Mei and Tin Shui Wai Drainage Basin (YLDMP) were completed in 1998.  The majority of the improvement works in Yuen Long and Kam Tin recommended under the YLDMP Study have been completed. Since completion of the DMP Studies, there have been changes in developments within the areas and new development proposals and town planning studies were commissioned. In addition, some new flooding complaints were received at the upstream areas of the drainage basins, indicating that further improvement to the drainage systems was required.

1.1.2        The Drainage Services Department (DSD) commissioned the “Review of Drainage Master Plans in Yuen Long and North Districts – Feasibility Study” (the Review Study) in 2008 so that the new development scenarios could be incorporated and the effectiveness of the previously recommended works could also be assessed. The Review Study completed in end 2011 identified that some areas in Yuen Long District could not meet the required flood protection level according to the latest land use changes and future developments taking into account various factors, including sedimentation at the downstream main channels, mangrove growth at river estuaries, updated extreme sea level statistics at Tsim Bei Tsui and projected climate change impacts, in the hydraulic analysis. To account for the severity and extent of possible flooding and the works implementation time, the Review Study proposed drainage improvement works in Yuen Long District.

1.1.3        Atkins China Ltd (ACL) was commissioned by the DSD in November 2013 to undertake an Investigation, Design and Construction Consultancy entitled “Agreement No. CE 22/2013 (DS) Drainage Improvement Works in Yuen Long, Stage 1 – Investigation, Design and Construction” (hereinafter called the Assignment). The Project comprises construction of drainage improvement works to four villages (namely Sung Shan New Village, Tai Wo, Lin Fa Tei and Ha Che) including landscaping, waterscaping, utilities diversion, temporary traffic arrangements, re-provisioning / improvements to existing dry weather flow intercepting system and any other works incidental to the completion of the Project.

1.1.4        An Environmental Impact Assessment (EIA) Study Brief (ESB-279/2014) for four villages namely Ha Che, Tai Wo, Lin Fa Tei and Sung Shan New Village which is a designated project was issued by the Environmental Protection Department (EPD) on 14 October 2014.

1.1.5        The EIA Report for Drainage Improvement Works Near Four Villages in Yuen Long – Sung Shan New Village, Tai Wo, Lin Fa Tei and Ha Che (referred to as “the Project”) (Register No. AEIAR-229/2021) was approved on 3 June 2021 and the Environmental Permit (EP) EP-596/2021, covering the Upgrading, Construction and Deepening of the Project was granted on 28 September 2021.

1.1.6        Aurecon Hong Kong Limited (Aurecon) is commissioned by the Wing Tat Civil Engineering Co. Limited to undertake the Environmental Team (ET) services and carry out the Environmental Monitoring and Audit (EM&A) for Drainage Improvement Works Near Four Villages in Yuen Long - Sung Shan New Village, Tai Wo, Lin Fa Tei and Ha Che (Register No. EP-596/2021).

1.1.7        This is the 3rd Quarterly EM&A Report summarizing the key findings of the construction phase EM&A programme from 1 August to 31 October 2024 (the reporting period) and is submitted to fulfil the requirements in Section 12.3 of the approved Updated EM&A Manual of the Project.

1.2        Construction Works Programme

1.2.1        The construction programme and the location plan of the Project are shown in Appendix 1.1 and Figure 1.1 respectively. The locations of the proposed drainage improvement work at the four villages are presented in Figures 1.2a to Figures 1.2d.

1.3        Project Organisation

1.3.1        Involvement of relevant parties in a collaborative and interactive manner is essential for the implementation of the recommended EM&A programme. The following sections outline the primary responsibilities and duties of the key EM&A programme participants. The lines of communication with respect to EM&A works are shown in Diagram 1.1.

A diagram of a company's work flow

Description automatically generated

Diagram 1.1 Organisation Chart

1.3.2        Parties with different levels of involvement in the Project organisation are summarized in Table 1.1.

Table 1.1 Parties Involved in Project Organisation

Parties

Organization / Company

Project Proponent

Drainage Services Department

Supervisor / Engineer’s Representative (ER)

Atkins China Ltd

Contractor

Wing Tat Civil Engineering Co. Limited

Environmental Team (ET)

Aurecon Hong Kong Limited

Independent Environmental Checker (IEC)

Mott MacDonald Hong Kong Limited

1.3.3        The key personnel contact names and numbers are summarized in Appendix 1.2.

1.4        Construction Works Programme and Construction Works Area

1.4.1        The construction works commenced on 20 February 2024. The construction works programme and the construction works area of the Project are shown in Appendix 1.1 and Figure 1.1 respectively.

1.5        Works undertaken during the Period

1.5.1        The main construction works carried out in the reporting period were as below.

Ha Che

§  Site Clearance Work

§  Breaking Ground;

§  Temporary Drainage Diversion

§  Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting; and

§  Sheet pilling & Backfilling and Compaction

Lin Fa Tei

§  Site Clearance Work

§  Breaking Ground;

§  Temporary Drainage Diversion; and

§  Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting

Tai Wo

§  No construction activities.

Sung Shan New Village

§  Site Clearance

§  Breaking Ground.

§  Temporary Drainage Diversion; and

§  Excavation and Lateral Support, Relocate/ Divert Utilities, Rebar Fixing, Formwork Erection and Cast-in, Concreting

1.5.2        The environmental mitigation measures corresponding to the main construction works implemented in the reporting period can be referred to Appendix 1.3.


 

2              Water Quality

2.1        Monitoring Requirement

2.1.1        In accordance with the approved Updated EM&A Manual, impact water quality monitoring should be carried out three days per week at all designated monitoring stations during the construction period.  The interval between two sets of monitoring should not be less than 36 hours.

2.1.2        Replicate in-situ measurements of dissolved oxygen (DO), temperature, pH, turbidity, salinity, water depth and suspended solids (SS) for each independent sampling event shall be collected to ensure a robust statistically interpretable database.

2.2        Monitoring Location

2.2.1        Impact water quality monitoring was conducted at 8 monitoring stations (excluded Station C4 & Station C5) during the reporting period which is summarized in Table 2.1. The location of water quality monitoring stations is shown in Figure 2.1a to Figure 2.1d.

Table 2.1 Summary of Impact Water Quality Monitoring Stations

Stream

Monitoring ID

Coordinates (HK Grid)

Remarks

Easting

Northing

SSNV

C1A (1)

821702

831945

Alternative Impact Monitoring Point

C2

822459

831470

Control Monitoring Point

C3A (2)

822413

831284

Alternative Control Monitoring Point

TW

C4 (4)

825497

830664

Control Monitoring Point

C5 (4)

825486

830716

Impact Monitoring Point

LFT

C6

827232

831713

Control Monitoring Point

C7A (3)

826865

832115

Alternative Control Monitoring Point

C8

826513

832075

Impact Monitoring Point

HC

C9

828304

835029

Control Monitoring Point

C10

827919

834271

Impact Monitoring Point

Notes:

(1)    At Station C1, access to safe sampling of water is not feasible due to steep banks on both sides of the stream channel.  An alternative monitoring location is proposed at Station C1A, which is about 250 m along the same stream channel downstream of Station C1 and is accessible for safe water sampling.

(2)    During the first day of baseline monitoring at Station C3, shallow water was observed, and the ET could not sample enough water for monitoring.  As agreed by the ER, the Contractor, and the IEC, a new sampling location, Station C3A, was identified at about 130 m upstream and was accessible for water sampling.

(3)    For Station C7, the location is not close to the nearest, revised works boundary (about 200 m away).  An alternative monitoring location is proposed at Station C7A, which is about 23 m upstream of the nearest, revised works boundary.

(4)    Construction works at Tai Wo are only allowed during dry season (i.e. October to March) in accordance with Condition 3.2 of EP No.: EP-596/2021. Due to no construction activities conducted at Tai Wo during the reporting period, no impact water quality monitoring at Tai Wo was carried out during the reporting period.

2.3        Monitoring Parameter and Frequency

2.3.1        The monitoring parameters, frequency and duration of impact water quality monitoring are listed in Table 2.2.

Table 2.2 Parameters measured in the Impact Water Quality Monitoring

Parameter

Frequency

Duration

Dissolved oxygen (DO), temperature, turbidity, salinity, pH, stream water depth and suspended solids (SS)

3 days in a week

Throughout the construction phase

2.3.2        Monitoring location and position, time, sampling depth, weather conditions and any special phenomena or work underway nearby are recorded during the impact monitoring.

2.4        Action and Limit Level for Water Quality Monitoring

2.4.1        The criteria of action and limit levels for water quality monitoring are defined in Table 2.3.

Table 2.3 Action and Limit Levels for Water Quality

Parameters

Action Level

Limit Level

DO in mg/L

< 5%-ile of baseline data

< 4 mg/L or < 1%-ile of baseline data

SS in mg/L

> 95%-ile of baseline data or >120% of upstream control station of the same day, whichever is higher

> 99%-ile of baseline data or 130% of upstream control station of the same day, whichever is higher

Turbidity in NTU

> 95%-ile of baseline data or >120% of upstream control station of the same day, whichever is higher

> 99%-ile of baseline data or > 130% of upstream control station of the same day, whichever is higher

Notes:

(1)    For DO, non-compliance of the water quality limit occurs when monitoring result is lower than the limit.

(2)    For SS and turbidity, non-compliance of the water quality limit occurs when monitoring result is higher than the limit.

(3)    All the figures given in the table are used for reference only and the EPD may amend the figures whenever it is considered necessary.

2.4.2        Based on the criteria listed in Table 2.3, the action and limit levels for water quality are determined in Table 2.4.

Table 2.4 Action and Limit Levels of Water Quality

Stream

Monitoring ID

Parameters

Action

Limit

SSNV

C1A

DO in mg/L

<6.72

<4 (1)

SS in mg/L

>7.3 or >120% of upstream control station of the same day, whichever is higher

>8.5 or > 130% of upstream control station of the same day, whichever is higher

Turbidity in NTU

>10.37 or >120% of upstream control station of the same day, whichever is higher

>10.81 or > 130% of upstream control station of the same day, whichever is higher

TW

C5

DO in mg/L

<8.36

<4 (2)

SS in mg/L

>9.9 or > 120% of upstream control station of the same day, whichever is higher

>10.0 or > 130% of upstream control station of the same day, whichever is higher

Turbidity in NTU

>13.64 or > 120% of upstream control station of the same day, whichever is higher

>13.87 or > 130% of upstream control station of the same day, whichever is higher

LFT

C8

DO in mg/L

<5.38

<4 (3)

SS in mg/L

>6.3 or > 120% of upstream control station of the same day, whichever is higher

>7.0 or > 130% of upstream control station of the same day, whichever is higher

Turbidity in NTU

>12.46 or > 120% of upstream control station of the same day, whichever is higher

>12.94 or > 130% of upstream control station of the same day, whichever is higher

HC

C10

DO in mg/L

<2.55

<2.43 (4)

SS in mg/L

>8.7 or > 120% of upstream control station of the same day, whichever is higher

>8.8 or > 130% of upstream control station of the same day, whichever is higher

Turbidity in NTU

>20.06 or > 120% of upstream control station of the same day, whichever is higher

>21.07 or > 130% of upstream control station of the same day, whichever is higher

Notes:

(1)    The 1%-ile of baseline DO data at C1A is 6.61 mg/L, which is higher than 4 mg/L.  Thus, DO concentration of 4 mg/L, which is in line with the Water Quality Objectives, is adopted as the limit level.

(2)    The 1%-ile of baseline DO data at C5 is 8.09 mg/L, which is higher than 4 mg/L.  Thus, DO concentration of 4 mg/L, which is in line with the Water Quality Objectives, is adopted as the limit level.

(3)    The 1%-ile of baseline DO data at C8 is 5.36 mg/L, which is higher than 4 mg/L.  Thus, DO concentration of 4 mg/L, which is in line with the Water Quality Objectives, is adopted as the limit level.

(4)    The 1%-ile of baseline DO data at C10 is 2.43 mg/L, which is lower than 4 mg/L.  Taking account of the baseline water quality condition and to minimise any false alarm of water quality deterioration during construction phase, DO concentration of 2.43 mg/L is adopted as the limit level.

2.5        Event and Action Plan

2.5.1        Should any non-compliance of the criteria occur, action in accordance with the Event and Action Plan in Appendix 2.1 shall be followed. Investigation of the exceedances of environmental quality performance limits should be conducted, and the ET will immediately notify the IEC and EPD, as appropriate.  The notification should be followed up with advice to the IEC and EPD on the results of the investigation, proposed actions and success of the action taken, with any necessary follow-up proposals.

2.6        Results and Observations

2.6.1        The detailed monitoring results during the reporting period are reported in the monthly EM&A Reports. The graphical presentation of water quality monitoring at the monitoring stations are shown in Appendix 2.2.

2.6.2        No Action or Limit Level exceedances was recorded during the reporting period. 

2.6.3        The summary of exceedance records of water quality monitoring during the reporting period is summarized in Table 2.5.

Table 2.5 Summary of Exceedance Records of Water Quality Monitoring

Parameter

No. of non-project related exceedances

Total No. of non-project related exceedances

No. of exceedance related to the Project

Total No. of exceedance related to the Project

AL

LL

AL

LL

Dissolved Oxygen

0

0

0

0

0

0

Turbidity

0

0

0

0

0

0

Suspended Solids

0

0

0

0

0

0

2.7        Quarterly Assessment of Construction Impacts on Suspended Solids at the Project Site

2.7.1        The comparison of the difference between the quarterly mean and 1.3 times of the ambient mean is presented in Table 2.6.

Table 2.6 Comparison of the difference between the quarterly mean and 1.3 times of the ambient mean

Parameter

Monitoring Location

Quarterly Mean of SS (mg/L)

Baseline Level of SS (mg/L)

1.3 Times of Ambient Mean (mg/L) (1)

Quarterly Mean of SS > 1.3 Times of Ambient Mean (Y/N)

Request of Further Mitigation Measures (Y/N)

Suspended Solids

C1A

2.7

4.8

6.2

N

N

C2 (Control Point)

3.9

3.2

4.2

N

N/A

C3A (Control Point)

4.0

2.2

2.9

Y

N/A

C6 (Control Point)

6.4

3.7

4.8

Y

N/A

C7A (Control Point)

9.1

6.7

8.7

Y

N/A

C8

3.1

4.0

5.2

N

N

C9 (Control Point)

4.1

5.9

7.7

N

N/A

C10

2.9

8.5

11.1

N

N

Notes:

(1)     1.3 times of the ambient mean equal to be defined as 30% increase of the baseline data.

 

Sung Shan New Village (Monitoring Locations C1A, C2 & C3A)

2.7.2        The quarterly mean of SS at Monitoring Location C1A (Impact Point) (2.7 mg/L) is lower than the 1.3 times of the ambient mean (6.2 mg/L). Hence, no further mitigation measures for control of water quality impact are required at Sung Shan New Village.

Lin Fa Tei (Monitoring Locations C6, C7A & C8)

2.7.3        The quarterly mean of SS at Monitoring Location C8 (Impact Point) (3.1 mg/L) is lower than the 1.3 times of the ambient mean (5.2 mg/L). Hence, no further mitigation measures for control of water quality impact are required at Lin Fa Tei.

Ha Che (Monitoring Locations C9 & C10)

2.7.4        The quarterly mean of SS at Monitoring Location C10 (Impact Point) (2.9 mg/L) is lower than the 1.3 times of the ambient mean (11.1 mg/L). Hence, no further mitigation measures for control of water quality impact are required at Ha Che.


 

3              Noise

3.1        Monitoring Locations

3.1.1        The monitoring locations for construction noise monitoring are listed in Table 3.1 and shown in Figure 3.1a to Figure 3.1d.

Table 3.1 Noise Monitoring Stations during Construction Phase

ID No. (1)

Location

Nature of Uses

Type of Measurement

SSNV_M2

Village house next to a nullah in Tong Tai Po Tsuen (near DD118 1720 S.A)

Residential

Façade

SSNV_M3

Village house near a soybean sauce factory in Sung Shan New Village (near DD118 1712)

Residential

Façade

SSNV_M6

#43, Sung Shan New Village

Residential

Free-field

TW_M2 (4)

#200, Cheung Po

Residential

Free-field

TW_M3 (4)

Kai Yip Garden, #3H, Tai Wo

Residential

Free-field

LFT_M1

#2G, Lin Fa Tei

Residential

Façade

LFT_M3A (2)

Near #125B, Lin Fa Tei

Residential

Free-field

LFT_M5

#156B, Lin Fa Tei

Residential

Façade

LFT_M6 (3)

Village house near the nullah (DD112 699 S.E)

Residential

Façade

LFT_M11 (2)

#210, Ngau Keng Tsuen

Residential

Façade

HC_M3A (2)

Next to DD111 326 S.B RP near Fan Kam Road

-

Free-field

HC_M4

#1C, Chuk Hang

Residential

Façade

HC_M6

The Arbutus House 12, #52, Shui Kan Shek

Residential

Façade

Notes:

(1)    SSNV – Sung Shan New Village; TW – Tai Wo; LFT – Lin Fa Tei; HC – Ha Che.

(2)    LFT_M3A, LFT_M11, HC_M3A and are alternative noise monitoring stations proposed to replace LFT_M3, LFT_M13 and HC_M3, respectively.

(3)    Due to the objection from property management office for providing access to designated monitoring location, the noise monitoring at LFT_M7 have been suspended since 27 March 2024. An alternative monitoring location LFT_M6 was proposed to replace LFT_M7 and agreed with the ER and the IEC.

(4)    Due to no construction activities conducted at Tai Wo during the reporting period, no impact noise monitoring at Tai Wo was carried out during the reporting period.

3.2        Noise Monitoring Parameter, Frequency and Duration

3.2.1        Construction noise level was measured by the ET and measured in terms of the A-weighted equivalent continuous sound pressure level (Leq).  Leq(30mins) used as the monitoring parameter for the construction noise monitoring. The monitoring should be conducted during the construction phase between 0700 and 1900 on normal weekdays at the designated monitoring locations.

3.2.2        As supplementary information for data auditing, statistical results such as L10 and L90 were also obtained for reference.

3.2.3        Table 3.2 summarizes the monitoring parameters, duration, and frequency of construction noise monitoring.

Table 3.2 Construction Noise Monitoring Parameter, Frequency and Duration

Monitoring Station

Parameter

Frequency and Duration

SSNV_M2, SSNV_M3, SSNV_M6, HC_M3A, HC_M4, HC_M6, TW_M2, TW_M3, LFT_M1, LFT_M3A, LFT_M5, LFT_M6 and LFT_M11

Leq(30mins) (as a logarithmic average of 6 consecutive Leq(5mins))

Once every week throughout the construction phase between 0700 and 1900 on normal weekdays

3.3        Action and Limit Levels

3.3.1        The Action and Limit levels were established in accordance with the approved Updated EM&A Manual. Table 3.3 presents the Action and Limit Levels for construction noise. Should non-compliance of the criteria occur, action in accordance with the Event and Action Plan presented in Appendix 3.1 shall be carried out.

Table 3.3 Action and Limit Levels for Construction Noise Monitoring

Time Period

Action

Limit Level

07:00 – 19:00 on normal weekdays

When one or more documented complaints are received

75 dB(A)(1)

07:00 – 23:00 on holidays; and

19:00 – 23:00 on all other days

45 dB(A)(2)

23:00 – 07:00 of the next day

30 dB(A)(2)

Notes:

(1)    Between 07:00 and 19:00, construction noise limit for school during normal term time is 70 dB(A) and 65 dB(A) during examination period.

(2)    The ASR of identified noise sensitive receivers is “A”, which is a rural area that is not affected by the in Influencing Factors (Ifs). The limit levels are stipulated in the Technical Memorandum on Noise from Construction Work in Designated Areas.

3.4        Results and Observations

3.4.1        The detailed monitoring results during the reporting period are reported in the monthly EM&A Reports. The graphical presentation of noise monitoring at the monitoring stations are shown in Appendix 3.2.

3.4.2        No Action or Limit levels exceedance was recorded in the reporting period.


 

4              Ecology

4.1        Freshwater Crab

4.1.1        With reference to the approved EIA Report (Register No.: AEIAR-229/2021), two freshwater crab species of conservation importance were recorded within the work sites during the ecological baseline survey. Somanniathelphusa zanklon was recorded at Lin Fa Tei and Ha Che, while Cryptopotamon anacoluthon was recorded in the upstream area at Ha Che. Both species are endemic to Hong Kong and considered to be “Endangered” and “Vulnerable” by the IUCN respectively (IUCN 2023). The construction activities of the project will disturb their natural habitats and potentially causing a direct loss of these two species due to their limited mobility.

Freshwater Crab Translocation Plan

4.1.2        Freshwater Crab Translocation Plan (FCTP) was prepared by an Ecologist with relevant experience in freshwater habitats and submitted to the EPD and the AFCD for their approval under Condition 2.8 of the EP. Any aquatic species of conservation importance found during the pre-construction surveys were translocated to suitable receptor sites outside of the proposed works area, and their condition and number was monitored to ensure their long-term survivorship after translocation. The EPD advised no further comment on the submitted FCTP on 9 February 2024. A formal reply letter was issued by the EPD on 4 July 2024 after the submission of hardcopy for their record.

Pre-construction Survey Results

Ha Che (CH.A 11.13 ~ CH.A 300.00)

4.1.3        The pre-construction survey was carried out at Ha Che on 5, 6 and 7 February 2024 prior to the commencement of construction works at Ha Che. A total of 11 freshwater crabs were collected, marked, and translocated from Ha Che. All these captured individuals were observed on the first (5 February 2024) and third (7 February 2024) nights of the three consecutive pre-construction surveys. No crabs were collected on 6 February 2024. Seven C. anacoluthon (four males and three females) were found particularly on the upper section of the works area within rocky substratum and leaf-litters, while four S. zanklon were noted on sections with soft silty-muddy substrate.

4.1.4        The captured endemic freshwater crabs were translocated to the identified receptor sites indicated in the approved Freshwater Crab Translocation Plan. C. anacoluthon were translocated in the section of shallow fast-flowing semi-natural watercourse with rocky substratum located south-east of Chuk Hang Village. Meanwhile S. zanklon were translocated to the section of shallow slow-flowing seminatural channel characterised soft soil substrate encompassed by a small patch of woodland and village houses. The receptor sites have comparable characteristics with the collection site.

4.1.5        Several aquatic invertebrates were also incidentally caught during the surveys. Among the observed aquatic invertebrates, larvae of species with conservation importance namely one Macromia berlandi, two Macromia urania and two Zygonyx iris were translocated to the proposed receptor sites. M. urania and M. berlandi were translocated to the receptor site for S. zanklon while Z. iris to the receptor site of C. anacoluthon.

Lin Fa Tei (CH.A0.00 ~ CH.A200.00)

4.1.6        The pre-construction survey was carried out at Lin Fa Tei in sections CH.A0.00 ~ CH.A200.00 on 11, 12 and 13 March 2024 prior to the commencement of construction works at Lin Fa Tei in sections CH.A0.00 ~ CH.A200.00. A freshwater crab was collected, marked, and translocated from Lin Fa Tei. The captured individuals were observed on the third (13 March 2024) night of the three consecutive pre-construction surveys. No crabs were collected on 11 and 12 March 2024. The captured C. anacoluthon was found by kick sampling within the stream bed roughly 5 meters downstream from the concrete water gate within section CH.A0.00 ~ CH.A200.00.

4.1.7        The captured endemic freshwater crab was translocated to the identified receptor site indicated in the approved Freshwater Crab Translocation Plan. The captured C. anacoluthon was translocated to a section of a shallow slow-flowing seminatural watercourse with silt and rocky substrate surrounded by agricultural lands at Lin Fa Tei which has comparable characteristics with the collection site.

4.1.8        A single individual of an adult Spotted Narrow-mouthed Frog was found on a slope in the eastern section of section CH.A0.00 ~ CH.A200.00. As the specimen is mobile and able to avoid the construction area once the construction work commences, it was not translocated to the receptor site.

Lin Fa Tei (CH.A200.00 ~ CH.A500.00 and CH.B0.00 ~ CHB.149.77)

4.1.9        The pre-construction survey was carried out at Lin Fa Tei in sections CH.A200.00 ~ CH.A500.00 and CH.B0.00 ~ CHB.149.77 on 17, 18 and 19 April 2024 prior to the commencement of construction works at Lin Fa Tei in sections CH.A200.00 ~ CH.A500.00 and CH.B0.00 ~ CHB.149.77. No freshwater crab was collected during the pre-construction survey.

4.1.10     Two individuals of adult Spotted Narrow-mouthed Frog were found during the surveys. As this specimen is mobile and able to avoid the construction area once the construction work commences, it was not translocated to the receptor site. The specimens were brought to nearby agricultural lands instead, which is the preferred habitat of the species.

Ha Che (CH.A300.00 ~ CH.A653.949)

4.1.11     The pre-construction survey was carried out at Ha Che in sections CH.A300.00 ~ CH.A653.949 from 11 to 13 September 2024 prior to the commencement of construction works at Ha Che in sections CH.A300.00 ~ CH.A653.949. A total of seven freshwater crabs were collected, marked, and translocated during the pre-construction survey.

4.1.12     A single C. anacoluthon was collected. Meanwhile, six S. zanklon were also collected during the pre-construction surveys. All crabs recorded were from the upper course, presumably due to the higher water quality of the section. Aside from individual BS1, most were noted as relatively mature which ranging from 19.8 to 29.1 mm.

4.1.13     Albeit the pre-construction surveys only targeted S. zanklon and C. anacoluthon, several fauna species were also unintentionally caught during the pre-construction surveys. A species of conservation importance recorded was also released to the proposed receptor site. A Chinese Soft-shelled Turtle was captured in the lower course of the stream section on the survey on 12 September 2024 and was quickly released at the lower receptor site.

4.1.14     Additionally, a single individual of C. anacoluthon was recorded in the lower receptor site on 11 September 2024 during the release of individual BS1. The individual lacks marking on its body and is therefore not an individual that was translocated from previous pre-construction surveys.

Post-translocation Monitoring

4.1.15     According to Section 5.2.5 of the approved Updated EM&A Manual for the Project, monthly post-translocation monitoring shall be conducted for at least 12 months after pre-construction surveys to monitor their establishment.

4.1.16     During the monitoring, active visual search by hand netting and kick sampling for aquatic fauna species would be performed at the respective receptor sites. Potential micro-habitats and hiding spaces that is favoured by the crabs such as rocks, organic debris, leaf litter, and riparian vegetation etc., will also be overturned or raked.

4.1.17     Upon discovery of any marked individuals from the pre-construction survey, date and time of capture, size and health condition of the individual will also be recorded once again.

4.1.18     The practice of mark and recapture of the translocated population of S. zanklon and C. anacoluthon at the receptor site can then be used to estimate population size, as well as inform the health and survival status of the translocated population.

4.1.19     Freshwater Crab Translocation Plan and Post-translocation Monitoring were carried out in the reporting period. The monitoring results are reported in the monthly EM&A Reports prepared for this Contract.

4.1.20     None of the translocated individuals from the pre-construction survey was found in the upper and lower receptor sites of Ha Che or the receptor site of Lin Fa Tei during the reporting period.

4.1.21     However, one new individual of S. zanklon without markings was captured at the receptor site Lin Fa Tei below the water gate where less vegetation is found in August 2024. This individual, however, was not the translocated individual as its details (i.e., carapace, sex and species) did not match with any of the translocated individuals in the record. This individual was released immediately after record.

4.1.22     In addition, 6 new individuals of C. anacoluthon without markings were captured at the Ha Che Upper and Ha Che Lower receptor site in October 2024. These individuals, however, were not the translocated individual as their details (i.e., carapace, sex and species) did not match with any of the translocated individuals in the record.


 

5              Waste Management

5.1.1        Waste generated from the Project include inert construction and demolition (C&D) materials and non-inert C&D wastes in the reporting period. The amount of waste generated by the construction works of the Project during the reporting period are shown in Appendix 5.1. 

5.1.2        Sorting of construction and demolition (C&D) materials was carried out on site.  Sufficient numbers of receptacles were provided for general refuse collection and sorting.  Excavated inert C&D materials were reused to minimize the disposal of C&D waste to public fill.

5.1.3        The Contractor is advised to minimize the wastes generated through recycling or reusing.  All applicable mitigation measures stipulated in the approved Updated EM&A Manual and waste management plans will be fully implemented.


 

6              Land Contamination

6.1.1        With reference to results of land contamination assessment included in the approved EIA Report (Register No.: AEIAR-229/2021), all identified sites with potential contamination are located outside the work area of the Project and no potential contamination arising from the proposed drainage improvement works is anticipated. Therefore, no land contamination issue is anticipated for this Project.

6.1.2        Mitigation measures listed in Appendix 1.3 should be adopted if any suspended contamination encountered during construction.

6.1.3        No suspected on-site contamination was observed or reported by the Contractor in the reporting period.


 

7              Landscape and Visual

7.1        Audit Requirements

7.1.1        According to the approved Updated EM&A Manual, site audits should be undertaken every week during the construction phase to check that the proposed landscape and visual mitigation measures are properly implemented and maintained as per their intended objectives. Mitigation measures recommended in the EIA Report as the audit requirements including, preservation of existing vegetation, transplanting of affected trees, compensatory tree planting, control of night-time lighting glare, erection of decorative screen hoarding and management of construction activities and facilities are summarized in Appendix 1.3.

7.2        Results and Observations

7.2.1        To monitor and audit the implementation of landscape and visual mitigation measures, 13 weekly landscape and visual site audits were carried out in the reporting period.

7.2.2        Environmental deficiencies regarding landscape and visual were observed on 2 & 30 October 2024. Key observations during the site audits on 2 & 30 October 2024 are summarized in Table 7.1.

Table 7.1 Site Observations

Date

Environmental Observations

Follow-up Status

2 Oct 2024

Observation(s) and Recommendation(s)

 

Sung Shan New Village:

1.      Fencing has to be added to protect tree.

 

 

Sung Shan New Village:

1.         Fencing has been added to protect tree during construction works.

30 Oct 2024

Observation(s) and Recommendation(s)

 

Sung Shan New Village

Fencing should be set up to protect tree.

 

 

 

The fencing is being set up by the contractor to protect tree.


 

8              Cultural Heritage

8.1        Archaeology

8.1.1        According to the assessment included in the approved EIA report (Register No.: AEIAR-229/2021) the proposed drainage works in the Lin Fa Tei area are located immediately adjacent to existing river course on mainly Pleistocene terraced alluvium and the western end of the alignment on Holocene alluvium between Lin Fa Tei Site of Archaeological Interest (SAI) and Shui Lau Tin SAI. The proposed works are partially located within Lin Fa Tei SAI.  Previous investigations within SAI have shown both in situ and secondary deposit and with potential for wooden features near the stream bed.  As per the recommendation from EIA report, Archaeological Survey shall be conducted prior to the construction works, the concerned area is marked in Figure 8.1.

8.1.2        A qualified archaeologist shall be engaged and apply for a licence under the Antiquities and Monuments Ordinance (Cap. 53) to conduct the Archaeological Survey prior to the construction phase. The scope and methodology of the Archaeological Survey shall be agreed with Antiquities and Monuments Office (AMO) prior to implementation. Tentatively and subject to agreement with AMO, a fieldscan, where possible, twenty auger tests and four 5 by 1m narrow trenches are proposed to further assess the archaeological potential of the area. If significant remains are uncovered, AMO should be notified and potential need for mitigation and/ or an appropriate way forward should be agreed by AMO and relevant parties.

8.1.3        For remaining drainage work areas (outside the area identified for Archaeological Survey) deemed to have limited (near Kam Sheung Road) to minimal (remainder of Works Areas) archaeological potential, AMO shall be informed immediately if antiquities or supposed antiquities are discovered during construction works for the proposed drainage improvement works for ascertaining required remedial works.

8.2        Built Heritage

8.2.1        According to the approved Updated EM&A manual, mitigation measures that should be implemented during the construction phase for graded historic buildings are presented in Table 8.1.

8.2.2        Condition surveys were carried out by qualified structural engineer for Lee Tat Bridge, Lan Fong Study Hall and St John’s Chapel prior to construction works. The Pre-construction Condition Survey Report were submitted to the EPD on 22 December 2023 under Condition 2.10 of the EP.


Table 8.1 Mitigation Measures for Impacted Graded Historic Buildings

Graded Historic Buildings

Mitigation Measures

Lee Tat Bridge, Shui Tsan Tin (Grade 3)

§   A condition survey should be carried out in advance of works and after completion of works by qualified building surveyor or structural engineer. The Condition Survey Report should contain descriptions of the structure, identification of fragile elements, an appraisal of the condition and working methods for any proposed monitoring and precautionary measures that are or were recommended with aid of photo records. The condition survey report must be submitted to the AMO for comment before construction activities commence and after the works have been completed. The contractor should implement the approved monitoring and precautionary measures.

§   Vibration, settlement and tilting monitoring should be undertaken during the construction works to ensure that safe levels of vibration are not exceeded.  An Alert, Alarm and Action (AAA) vibration limit set at 5 / 6 / 7.5 mm/s for Grade 3 historic buildings, settlement limit set at 6/ 8/ 10mm, and tilting limit set at 1/2000; 1/1500; 1/1000 should be adopted. Monitoring proposal, including checkpoint locations, installation details, response actions for each of the AAA levels and frequency of monitoring should be submitted for AMO's consideration. Installation of monitoring checkpoints shall be carried out in great care and adequate protection shall be provided so as to avoid unnecessary disturbance/ damage to the historic fabrics.  Photo records of monitoring checkpoints shall be submitted upon installation for AMO's records. Monitoring records should be submitted to AMO on regular basis and alert AMO should the monitoring reach AAA levels.

Lan Fong Study Hall, Chuk Hang (Grade 3)

St John’s Chapel, Cheung Po (Grade 2)

 


 

9              Environmental Site Inspection and Audit

9.1        Implementation Status of Environmental Mitigation Measures

9.1.1        Site audits were carried out by ET on weekly basis at least once per week to monitor the implementation of proper environmental management practices and mitigation measures in the Project site.

9.1.2        Total 13 site inspections were carried out during the reporting period. No outstanding issues were reported during the reporting period. Details of observations recorded during the site inspections are presented in Table 9.1.

Table 9.1 Site Observations

Date

Environmental Observations

Follow-up Status

7 Aug 2024

Observation(s) and Recommendation(s)

 

Nil

 

 

Nil

14 Aug 2024

Observation(s) and Recommendation(s)

 

Nil

 

 

Nil

21 Aug 2024

Observation(s) and Recommendation(s)

 

Lin Fa Tei:

1.      Geotextiles should be maintained in good condition and right position.

 

 

Lin Fa Tei:

1.      Geotextiles was maintained in good condition and the right position.

27 Aug 2024

Observation(s) and Recommendation(s)

 

Nil

 

 

Nil

4 Sep 2024

Observation(s) and Recommendation(s)

 

Lin Fai Tei:

1.      Geotextiles should be maintained in good condition and the right position.

 

 

Lin Fai Tei:

1.      Geotextiles was maintained in good condition and the right position by the contractor.

11 Sep 2024

Observation(s) and Recommendation(s)

 

Sung Shan New Village:

1.      Relocation of EP and CMP to a more obvious area on site instead of placing it at the resting area.

 

 

Sung Shan New Village:

1.      The relevant permit and license were properly displayed at a more obvious area on site by the contractor.

19 Sep 2024

Observation(s) and Recommendation(s)

 

Ha Che:

1.      The decolorized NRMM label should be replaced with a proper label.

2.      The pump of the wastewater recycling system should be maintained in good condition to prevent overflow.

 

 

Ha Che

1.      The decolorized NRMM label was replaced with a proper label by the contractor.

2.      The pump of the wastewater recycling system was maintained in good condition to prevent overflow.

25 Sep 2024

Observation(s) and Recommendation(s)

 

Lin Fa Tei:

1.      Geotextiles should be kept intact and undamaged.

 

 

Lin Fa Tei:

1.      Geotextiles were kept intact and undamaged by the contractor.

2 Oct 2024

Observation(s) and Recommendation(s)

 

Sung Shan New Village:

1.      Fencing has to be added to protect tree.

 

 

Sung Shan New Village:

1.      Fencing has been added to protect tree during construction works.

9 Oct 2024

Observation(s) and Recommendation(s)

 

Nil

 

 

Nil

16 Oct 2024

Observation(s) and Recommendation(s)

 

Nil

 

 

Nil

23 Oct 2024

Observation(s) and Recommendation(s)

 

Nil

 

 

Nil

30 Oct 2024

Observation(s) and Recommendation(s)

 

Sung Shan New Village:

1.      Fencing should be set up to protect tree.

 

 

Sung Shan New Village:

1.      The fencing is being set up by the contractor to protect tree.

9.1.3        According to the EIA Study Report, Environmental Permit, contract documents and approved Updated EM&A Manual, the mitigation measures detailed in the documents should be implemented as much as practical during the reporting period. An updated Implementation Status of Environmental Mitigation Measures (EMIS) is provided in Appendix 1.3.


 

10        Summary of Monitoring Exceedance, Complaints, Notification of Summons and Prosecutions

10.1   Summary of Exceedance

Water Quality Monitoring

10.1.1     The summary of exceedance records of water quality monitoring during the reporting period is summarized in Table 10.1.

Table 10.1 Summary of Exceedance Records of Water Quality Monitoring

Parameter

No. of non-project related exceedances

Total No. of non-project related exceedances

No. of exceedance related to the Project

Total No. of exceedance related to the Project

AL

LL

AL

LL

Dissolved Oxygen

0

0

0

0

0

0

Turbidity

0

0

0

0

0

0

Suspended Solids

0

0

0

0

0

0

10.1.2     No Action Level or Limit Level exceedance was recorded during the reporting period.

Noise Monitoring

10.1.3     No Action Level or Limit Level exceedance was recorded during the reporting period.

10.2   Summary of Environmental Non-Compliance

10.2.1     No environmental non-compliance was recorded in the reporting period.

10.3   Summary of Environmental Complaint

10.3.1     No environmental complaint was received in the reporting period. The Cumulative Complaint Log is presented in Appendix 10.1.

10.4   Summary of Environmental Summon and Successful Prosecution

10.4.1     There was no successful environmental prosecution or notification of summons received since the Project commencement. The Cumulative Log for environmental summon and successful prosecution is presented in Appendix 10.1.


 

11        Conclusions and Recommendations

11.1   Conclusion

11.1.1     This 3rd Quarterly EM&A Report presents the EM&A works during the reporting period from 1 August to 31 October 2024 in accordance with the approved Updated EM&A Manual.

11.1.2     Water Quality Monitoring was conducted during the reporting period. No Action or Limit Level exceedance was recorded during the reporting period.

11.1.3     Construction noise monitoring was carried out during the reporting period. No Action Level or Limit Level exceedance was recorded for construction noise monitoring in the reporting period.

11.1.4     Post-translocation monitoring was conducted during the reporting period. None of the translocated individuals from the pre-construction survey was found in the upper and lower receptor sites of Ha Che or the receptor site of Lin Fa Tei during the reporting period. However, one new individual of S. zanklon without markings was captured at the receptor site Lin Fa Tei below the water gate where less vegetation is found in August 2024. This individual, however, was not the translocated individual as its details (i.e., carapace, sex and species) did not match with any of the translocated individuals in the record. This individual was released immediately after record.

11.1.5     In addition, 6 new individuals of C. anacoluthon without markings were captured at the Ha Che Upper and Ha Che Lower receptor site in October 2024. These individuals, however, were not the translocated individual as their details (i.e., carapace, sex and species) did not match with any of the translocated individuals in the record.

11.1.6     Total 13 environmental site inspections and 13 landscape and visual site audits were carried out in the reporting period. Recommendations on mitigation measures were given to the Contractor for remediating the deficiencies identified during the site inspections.

11.1.7     No environmental complaint was received in the reporting period.

11.1.8     No notification of summons and successful prosecutions were recorded in the reporting period.

11.1.9     The EM&A methodology has been effective in monitoring the environmental impacts of the Project and the effectiveness of the mitigation measures. The data collected were useful in determining whether the Project had caused unacceptable impacts on the sensitive receivers. Analysis of all EM&A data collected throughout the baseline and the impact monitoring periods demonstrated the environmental acceptability of the Project.

11.2   Comments/ Recommendations

11.2.1     The key environmental mitigation measures for the Project in the coming reporting period expected to be associated with the construction activities include:

Noise

 

§  Only well-maintained plant should be operated on-site, and plant should be maintained regularly during the construction programme; and

§  Quality Powered Mechanical Equipment (QPME) should be adopted as far as possible.

Water Quality

 

§  No effluent discharge would be allowed before acquired the effluent discharge license;

§  Surface run-off from construction sites should be discharged into dedicated discharge point via adequately designed sand/ silt removal facilities;

§  Channels/ earth bunds/ sandbags barriers should be provided on site to properly direct stormwater to silt removal facilities;

§  Silt removal facilities, channels and manholes should be maintained, and the deposited silt and grit should be removed regularly;

§  Open stockpiles of construction materials on sites should be covered with tarpaulin or similar fabric during rainstorms; and

§  Perimeter channels should be provided on site boundaries where necessary to intercept stormwater run-off from outside the site so that it will not wash across the site.

Waste Management

 

§  Provision of sufficient waste disposal points and regular collection of waste;

§  Regular cleaning and maintenance programme for drainage system; and

§  Chemical containers shall be stored with drip tray underneath.

Ecology

 

§  Minimize loss of habitats and associated wildlife; and

§  Using directional lighting to prevent excessive light spill into adjacent natural habitat and disturbance to nocturnal fauna.

Landscape and Visual

 

§  Construction activities shall be carefully designed to minimize impact on existing retained trees; and

§  Adequate tree protection measures shall be provided for the trees to be retained on site.

11.2.2     The proposed mitigation measures were properly implemented and were considered effective and efficient in pollution control.